Gò Vấp flyover in HCM City completed

by 01 November 2017 Last updated at 08:59 AM

The second bridge of the Y-shaped flyover in HCM City’s Gò Vấp District connecting Phạm Ngũ Lão and Nguyễn Oanh streets opened to traffic on October 31.

 

The Y-shaped Gò Vấp flyover in HCM City built at a cost of VNĐ 406 billion ($17.88 million) has been completed two months ahead of schedule, and is helping ease congestion on major roads leading to Tân Sơn Nhất Airport. VNA/VNS Photo Hoàng Hải
Viet Nam News

HCM CITY — The second bridge of the Y-shaped flyover in HCM City’s Gò Vấp District connecting Phạm Ngũ Lão and Nguyễn Oanh streets opened to traffic yesterday.

It cost more than VNĐ 57 billion (US$2.51 million) and almost five months to build, two months fewer than scheduled.

The two-lane bridge is 280 metres long and six metres wide, and allows vehicles to travel one-way to Nguyễn Oanh.

The steel flyover, which cost a total of VNĐ406 billion ($17.88 million), has another bridge connecting Nguyễn Oanh and Nguyễn Kiệm Streets that opened to traffic last January.

It is helping ease congestion at the Gò Vấp intersection and major roads leading to Tân Sơn Nhất International Airport. —VNS

 

 

 

 

 

 

 

 

Top VND Exchange Rates

Auto-refesh 15m

USD

EUR

AUD
1 VND
Inverse:
0.00004
22,510.0
0.00004
25,226.0
0.00006
15,674.0

Mid-market rates: 2024-04-29 08:01 UTC

WEATHER FORECAST