The private unit is speeding up site clearance and focusing resources to launch the project.
Many important transmissions accessories and two super transformers have arrived at Vĩnh Tân International Airport on Monday for assembly.
This 600-million-USD project is expected to be completed and put into use by 2020. Ninh Thuận has 34 renewable energy projects licensed for investment.
Fifteen of them have been put into operation, but their capacity was cut from 10 to 60% due to grid overload.