The remaining uncleared grounds are mainly sandwiched between residential land, houses, and locations with difficult access for construction.
80% of the construction of three resettlement areas in Hòa An, Hòa Trị and Hòa Bình communes has been completed. This will help ensure the arrangement of accommodation for more than 100 resettled households is completed before June 30.
The remaining nine resettlement sites in Tuy An districts, Song Cau town, and Dong Hoa are being urgently prepared for construction. According to the plan, by June 30, Phu Yen must hand over 100% of the site to the investor./.