Thua Thien Hue disburses 26.3% of public investment in five months

by NDO18 June 2023 Last updated at 20:39 PM

Comments0
Thua Thien Hue disburses 26.3% of public investment in five months
Nguyen Hoang Bridge project has a good disbursement progress in Thua Thien Hue.
VTV.vn - The central province of Thua Thien Hue disbursed over 1.55 trillion VND in the first five months of this year, reaching 26.3% of the yearly target, a higher disbursement rate than the national average.

The province disbursed 20.6% of the local budget, 39.3% of the central budget, and 29.4% of ODA capital during the January-May period.

Despite a higher disbursement rate than the national average, the rate has yet to reach the set target, due to the prolonged time of land clearance of public projects, fluctuating prices of construction materials, and the scarcity of supply for sand and soil.

Issues such as the appraisal of fire prevention and fighting, environmental impacts, and weak capacity of contractors, have also affected the project and disbursement progress.

The province will adjust its capital plan in 2023 to shift public capital from low-disbursed projects to projects with high disbursement rates.

Related departments and agencies are also required to shorten the project appraisal time to two-thirds of the current time.