According to the municipal Transport Construction Investment Project Management Board, the city is simultaneously implementing seven projects, namely Tu Lien, Ngoc Hoi, Tran Hung Dao, Thuong Cat, Van Phuc, Hong Ha and Me So bridges. Construction is being carried out on multiple fronts, focusing on bored piles, pile caps, piers and superstructure works.
Among them, component project 2 of Tu Lien Bridge has handed over over 80% of the required site area, with key foundation works largely completed and superstructure construction underway.
Ngoc Hoi Bridge has also made notable progress, completing most main pier piles and advancing substructure and beam casting works.
Tran Hung Dao Bridge is being executed in parallel across its main and approach sections after receiving over 77% of the site area, with nearly all households agreeing to handover. Thuong Cat Bridge has maintained stable progress, while Van Phuc Bridge, benefiting from completed site clearance, has accelerated construction across major components.
For the Me So bridge, municipal leaders instructed relevant units to closely manage site clearance and construction support infrastructure.
For the Ngoc Hoi bridge, the requirement is to thoroughly review bottlenecks related to land and technical infrastructure and promptly adopting solutions to address any delays.
At the same time, authorities emphasised that progress must go hand in hand with quality, safety and durability.
Hung Yen province must complete site clearance for the remaining agricultural land by June 30 and residential land by July 15. Meanwhile, Hanoi’s Department of Agriculture and Environment is tasked with coordinating the clearance of pressure relief wells within the right-bank Red River dyke corridor by May 10.
Despite steady construction progress, recent reports indicate that additional site handover remains limited in some key areas, continuing to pose a major bottleneck. The city has urged local authorities to expedite clearance of remaining land and complete relocation of underground and overhead infrastructure in line with set deadlines.
Under pressing timeline requirements, the city has urged communes and wards involved in the Tu Lien, Ngoc Hoi, Tran Hung Dao and Thuong Cat bridge projects to expedite clearance of the remaining land in line with previous directions of the municipal Party Committee, while completing the relocation of underground and overhead infrastructure by May 15.
The simultaneous development of seven Red River bridges is expected to mark a major step forward in Hanoi’s transport infrastructure, enhancing regional connectivity, easing pressure on existing crossings and opening up new urban development space along both riverbanks.