Cat Linh - Ha Dong urban railway undergoes 20-day test run

by VTV418 December 2020 Last updated at 00:00 AM

Comments0
Cat Linh - Ha Dong urban railway undergoes 20-day test run
VTV.vn - With 13 trains and a frequency of 6-7 minutes per trip, roughly 300 test runs of the Cat Linh- Ha Dong train are currently being carried out daily.

The test runs will be done for 20 days before going into official operation. The process is being supervised by French consultants and the operator's representative.

During the test operation, hypothetical situations are being run including a train fire, passengers poking their heads out the window, and other obstacles while operating. The entire process, from operating the trains to connecting to other systems, is being supervised by French ACT Consultants.

The Ministry of Transport is determined to start commercial operations in January 2021.